Line Clearance at Packaging Area Procedure

Line Clearance , Purpose:

Line Clearance , To lay down the Procedure for Line Clearance at the Packaging Area.

Line Clearance , Scope:

This SOP is applicable for the Packaging Area of XX Pharmaceuticals Limited.

Definition / Abbreviation:

Line Clearance : Line Clearance is a method of assuring components, labels, and documents have been removed and accounted from the previous work order for before starting a new work order and to make certain the line is properly prepared for the next work order.

Responsibilities:

[][]The Roles and Responsibilities are as follows:

Operator

[][]To follow the laid down procedure

Executive, Packaging

[][]To monitor and check the laid down procedure

Manager, Production

[][]To implement this correctly

Manager, Quality Assurance

[][]To approve the Document

Procedure:

Precautions:

[][]Ensure the proper safety instructions are followed.
[][]Ensure that no previous product is available in the area.
[][]Line Clearance during Product to Product Changeover
[][]Clean all utility lines like compressed air line, air inlet ducts and return air risers with dry mop to remove loose dust from the floor.
[][]Clean the door, floor, walls and ceiling with dry cloth & finally wet mop.
[][]Area cleaning activity is recorded in ‘Room Cleaning Log book’
[][]Clean all equipment in the area according to their respective SOPs and no traces of previous product are visible within the equipment.
[][]Check and ensure that equipment cleaning activity is recorded in respective ‘Equipment Log Book’
[][]Ensure that Span between equipment usage and cleaning is not more than seventy two hours.
[][]Balances, if available in the packaging area, are cleaned and accuracy check is done before use.
[][]Fresh set of gowns are issued to concerned operators.
[][]Proper environmental condition is maintained in the area and the records of the same are maintained in the specified formats.
[][]Ensure the correctness of Batch Packaging Record.

Line Clearance during Batch to Batch Changeover

[][]Ensure that previous batch material is removed from the packaging area.
[][]Ensure that all equipment and their spares are cleaned according to their respective SOPs.
[][]Ensure that equipment cleaning activity is recorded in respective ‘Equipment Log Book’.
[][]Ensure that floor is cleaned using vacuum cleaner and no visible traces of the previous batch materials on the floor.
[][]Proper environmental condition is maintained in the area and the records of the same are maintained in the specified formats.
[][]Ensure the correctness of Batch Packaging Record.

Annexure:

Annexure I Equipment Use Log Book

Line Clearance at Packaging Area Procedure Read More »

Temperature and Relative Humidity Monitoring at Packaging Area

Temperature and Relative Humidity Monitoring, Purpose:

Temperature and Relative Humidity Monitoring, To lay down the procedure for monitoring of Temperature & Relative Humidity (%) at the Packaging area.

Temperature and Relative Humidity Monitoring, Scope:

This SOP is applicable for the Packaging Area of XX Pharmaceuticals Limited.

Definitions / Abbreviation:

N/A.

Responsibilities:

[][]The Roles and Responsibilities are as follows :

Operator

[][]To follow the laid down procedure

Executive, Packaging

[][]To monitor and check the procedure is followed

Manager, Production

[][]To implement this correctly

Manager, Quality Assurance

[][]To approve the Document

Annexure:

N/A.

Procedure :

Precaution :

[][]Do not use a new hygrometer unless it is calibrated.
[][]When any hygrometer is shifted from one location to another, allow to stabilize the device prior to record the temperature / Relative Humidity (%).
[][]Check the due date of calibration of the hygrometer and magnehelic gauge before taking reading.
[][]Ensure that temperature and Relative Humidity (%) readings are taken before going to operation.
[][]Temperature and Relative Humidity (%) (using Digital Hygrometer)
[][]Ensure that no dust is accumulated over the sensor.
[][]Read the temperature and relative humidity (%) values displayed on the screen of digital hygrometer and record.

Area

[][]Packing Hall, Waste, Cleaner’s, Printing, IPC Room, Office Executive and Packing Material Staging.

Temperature

[][]NMT 25°C

Relative Humidity (%)

[][]NMT 60 %

Frequency

[][]Twice in a shift, first before starting the operation and second after four hours.
[][]If the reading is not within limit at any time of operation, inform the Engineering department immediately.

Temperature and Relative Humidity Monitoring at Packaging Area Read More »

Packaging Area Cleaning Procedure

Packaging Area Cleaning, Purpose:

Packaging Area Cleaning, To lay down the procedure for effective cleaning at the Packaging Area.

Packaging Area Cleaning, Scope:

This SOP is applicable for the Packaging Area of XX Pharmaceuticals Limited.

Definitions / Abbreviation:

[][]N/A.

Responsibilities:

[][]The Roles and Responsibilities are as follows:

Operator

[][]To follow the laid down procedure

Executive, Packaging

[][]To monitor and check the cleanliness of area

Manager, Production

[][]To implement this correctly

Manager, Quality Assurance

[][]To approve the Document

Procedure:

Precaution:

[][]Do not clean/disinfect the area when the packing is running.
[][]Keep the cleaning agents at the designated place only with proper labels.
[][]Ensure that after usage the wet mops are washed and hanged in hanger in cleaner store & allowed to dry. Ensure other cleaning tools are also hanged in hanger after use.
[][]After use of cleaning agent wash hands, feet and fingers thoroughly with soap & plenty of water.
[][]Ensure that during cleaning all the product containers are closed.
[][]Check and ensure that disinfectant solution prepared is not stored for use for the next day and the residue is discarded by pouring into drain.
[][]At least two different disinfectants are to be used alternatively on weekly basis..
[][]Do not mop the floor after keeping Cleaned equipment in clean equipment storage room.

Cleaning Tools / Agents

[][]Portable vacuum cleaner
[][]Cloth & wiper
[][]Potable water
[][]Glass Cleaning agent: ‘Clear View’ (Brand Name).
[][]Disinfectant (Savlon/ Dettol/ Chlotec).
[][]Floor cleaning agent Perfect 7/Enviro Care
[][]Preparation of 2.5 % v/v Chlorhexidine Gluconate Solution
[][]To make 10 L disinfectant solution take 2.5 L Chlorhexidine Gluconate in freshly collected purified water to make up volume up to 10 L).
[][]Stir well to mix the solution properly.
[][]Prepare the disinfectant solution separately in separate bucket for use in different floor.
[][]Maintain the ‘Disinfectant Solution Preparation Record’.

Product to Product Cleaning Procedure (Type-A Cleaning) for Secondary Packaging Area

[][]Type – A cleaning is defined as cleaning procedure followed during product to product changeover.
[][]If the unit/equipment is used for same product it has to be cleaned after 72 hours.
[][]Place the status label ‘TO BE CLEANED’  in the Area.
[][]Clean the ceiling, walls, light fixtures, supply diffusers (SD) and return grills (RG) first with portable
[][]Vacuum cleaner to remove loose dust using a platform trolley, then with wet mop.
[][]Clean the machine/Equipment in packaging are As per SOP.
[][]Clean the doors, windows, compressed air lines and other service lines with dry cloth and then wet mop.
[][]Clean the glasses with ‘Clear View’ solution and wipe.
[][]Clean the control panels, electrical wires with dry cloth.
[][]Clean toolbox, table, log books, SOP folders, hygrometer, stool / chair with dry Cloth.
[][]Clean the floor first with dry mop, then with Perfect 7/Enviro Care and finally with potable water.
[][]Ensure after inspection for absence of any residue of previous product. If any residue of previous product or extraneous matter is found, re-clean the area using above procedure until the area is free of any residue/ extraneous matter.

[][]Remove ‘TO BE CLEANED’ and affix ‘CLEANED’ label in the cleaned area.
[][]Record the cleaning activity in ‘Room Cleaning Log Book’.

Frequency of Cleaning

[][]During product to product change over.
[][]If 72 hours time exceeds after cleaning and the equipment or area is not used, use the equipment or area after performing B-type cleaning.

Batch to Batch Cleaning (Type-B Cleaning) for Secondary Packaging area

[][]Type – B cleaning is defined as cleaning procedure followed during batch to batch changeover of a particular product.
[][]Place the equipment status label ‘PARTIALLY CLEANED’  in the area.
[][]First Clean the floor, ceiling, walls, light fixtures, supply diffusers (SD), return grills (RG) doors, windows and equipment with portable vacuum cleaner to remove the loose dust. Finally clean the floor with wet mop.
[][]Remove ‘PARTIALLY CLEANED’ label and affix ‘CLEANED’ label in the area.
[][]Record the cleaning activity in ‘Room Cleaning Log Book’.

Frequency of Cleaning

[][]During batch to batch change over.

Cleaning at the End of Day’s Operation

[][]Clean external parts of the machine, and operating panel with dry cloth.
[][]Clean the floor first with dry mop and finally with disinfectant solution.
[][]Frequency of Cleaning
[][]At the end of the day’s work.

Packaging Area Cleaning Procedure Read More »

Transfer of Finished Goods to the Finished goods storage area

Transfer of Finished Goods, Purpose:

Transfer of Finished Goods, To lay down the procedure for to the Finished Goods Storage Area.

Transfer of Finished Goods, Scope:

This SOP is applicable for the Packaging Area of XX Pharmaceuticals Limited.

Definitions / Abbreviation:

[][]N/A

Responsibilities:

[][]The Roles and Responsibilities are as follows:

Operator

[][]To follow the laid down procedure

Executive, Packaging

[][]To monitor and check the laid down procedure

Manager, Production

[][]To implement this correctly

Head of Quality Assurance

[][]To approve the Document

Annexure:

Annexure I – Finished Goods Transfer Note.
Annexure II – Weight Checking Record of Inner Carton
Annexure III – Weight Checking Record of Shipper Carton

Procedure:

Precautions:

[][]Do not transfer finished goods to the Finished Goods Storage area without Quality Compliance (QCOM) approval.
[][]Warehouse personnel should not receive finished goods from Production without any ‘Finished Goods Transfer Note’.
[][]Ensure that proper labels are on shipper carton & pallet.
[][]Check the weight of individual inner carton and keep record at 30 minutes interval in Annexure-II (Weight Checking Record of Inner Carton).
[][]Attach the Transparent Hologram Sticker on inner carton.
[][]Place the inner cartons in shipper carton and seal the shipper carton using gum tape.
[][]Check and ensure that ‘PRODUCT LABEL’  of shipper carton (Product name, Batch No., Mfg. Date, Exp. Date, Pack Quantity, Sr. No., Packed by, Storage Condition) is legible and clear.
[][]Check the weight of individual shipper carton and keep record of every shipper carton’s weight in Annexure-III (Weight Checking Record of Shipper Carton).
[][]Seal on every shipper carton as the following using rubber stamp (L-3.25 inch X W-2.0 inch) and record the relevant information which corresponds with Annexure-III.

SHIPPER CARTON NO.:………………….

WEIGHT:……………………………………….

NAME:…………………………………………..

SIGNATURE AND DATE:……………….

[][]Keep the shipper cartons on a clean pallet. Use more than one pallet if required to keep shipper cartons on it.
[][]In case of Loose shipper carton affix ‘LOOSE LABEL’  on two sides of shipper carton (Front & Back).
[][]Prepare a ‘Finished Goods Transfer Note’ after completion of packing of a batch as per format (Annexure – I).
[][]QCOM shall affix ‘QUARANTINED’ label on pallet.
[][]When the batch is approved by Quality Compliance (QCOM), hand over the batch along with Finished Goods Transfer Note to warehouse personnel.
[][]Maintain batch details in ‘Finished Goods Register’ Production personnel will sign as ‘Transferred by’ and warehouse personnel as ‘Received by’ in the Finished Goods Register.

Annexure:

Annexure I – Finished Goods Transfer Note.
Annexure II – Weight Checking Record of Inner Carton
Annexure III – Weight Checking Record of Shipper Carton

Transfer of Finished Goods to the Finished goods storage area Read More »

Material Drying Machine Set Up, Operation & Cleaning

Material Drying Machine , Purpose :

Material Drying Machine , The purpose of this SOP is to describe the setting, operation and cleaning procedure of Material Drying Machine (Model: Standard) in order to comply with cGMP standard.

Material Drying Machine , Scope :

The scope of the procedure is applicable to the Material Drying Machine (Model: Standard) at the Production area of XX Pharmaceuticals Limited.

Definitions / Abbreviation:

[][]N/A.

Responsibilities:

[][]The Roles and Responsibilities are as follows:

Operator

[][]Sep Up, Operation and cleaning of the Material Drying Machine (Model: Standard)
[][]Maintaining Equipment Log Book

Executive, Production

[][]To monitor and check the laid down procedure.

Manager, Production

[][]To implement this correctly

Manager, Quality Assurance

[][]To approve the Document

Procedure

Precautions :

[][]Make sure that the main power switch is OFF position before and after operation.
[][]Use face mask, rubber gloves and protective clothing during handling of materials.
[][]Check the cleanliness of individual tray and machines inner part during assembling of machine.
[][]Booth side doors are in lock position during operation.
[][]Check the air outlet damper position before and after completion of operation.

Machine Assembling

[][]Keep the necessary change parts near the material dryer machine before assembling.
[][]Assemble the dryer by opening the front side door of the dryer.
[][]Load the tray with material and place into the tray holding rack.
[][]Then set the rack carrying trolley.
[][]Then place the tray holding rack into the machine.
[][]After that closed the door accurately with the help of door locking handle.
[][]Then closed the air outlet damper and tight the screw accurately.

Machine Operation

[][]Switch ON the main power switch.
[][]Open the plastic cover and set the desire temperature of the machine.
[][]Then open the plastic cover and set the desire time of the machine.
[][]At first switch ON the blower of the machine.
[][]Then switch ON the heater of the machine.
[][]After completed the drying time open the air outlet damper for material cooling and check the LOD.
[][]After operation switch OFF the heater and then blower. Unload the tray holding rack from the machine.
[][]Finally switch OFF the main power of the machine.
[][]Record the machine operation parameters in the ‘Equipment Log Book’.

Machine Dismantling

[][]Open the both side door of the machine.
[][]Unload the tray holding rack from the machine with the help of carrying trolley.
[][]Remove the tray from the rack.

Machine Cleaning

[][]Remove dusts from the machine body and other necessary parts with a vacuum cleaner.
[][]Clean all the machine parts with dry lint free cloth.
[][]Use potable water to clean the machine body, product contact parts, tray and other machine parts.
[][]Use hot water to clean all the trays.
[][]Finally rinse the machine body, product contact parts, trays and other machine parts with purified water.
[][]Remove the water with lint free cloth.
[][]After final cleaning affix the ‘CLEANED’ label.
[][]Record the cleaning parameters in the ‘Equipment Log Book’.

Annexure:

Annexure I Equipment Use Log Book

Material Drying Machine Set Up, Operation & Cleaning Read More »

Material Pulverization Machine Set Up, Operation & Cleaning

Material Pulverization Machine, Purpose :

Material Pulverization Machine, The purpose of this SOP is to describe the setting, operation and cleaning procedure of the Material Pulverization Machine (Model: 30B) in order to comply with cGMP standard.

Material Pulverization Machine, Scope :

The scope of the procedure is applicable to the Material Pulverization Machine (Model: 30B) at the Production area of XX Pharmaceuticals Limited.

Definitions / Abbreviation:

[][]N/A.

Responsibilities:

[][]The Roles and Responsibilities are as follows:

Operator

[][]Sep Up, Operation and cleaning of the Material Pulverization Machine (Model: 30B)
[][]Maintaining Equipment Log Book

Executive, Production

[][]To monitor and check the laid down procedure.

Manager, Production

[][]To implement this correctly.

Manager, Quality Assurance

[][]To approve the Document.

Procedure
Precautions :

[][]Make sure that the main power switch is OFF position before and after operation.
[][]Use face mask, rubber gloves and protective clothing during handling of materials.
[][]Check the cleanliness of sieves, ss container, tray and gasket before assembling of machine.
[][]Check the sieve for its integrity before and after completion of operation.

Machine Assembling

[][]Keep the necessary change parts near the machine before assembling.
[][]Assemble the machine by opening the front side cover of the machine.
[][]Adjust the sieve into the ring with the help of screw.
[][]Then set the sieve ring into the machine.
[][]Close the cover of the machine properly.
[][]Set the filter bag of the machine with the help of spring and clamp.
[][]Place the tray under the filter bag.

Machine Operation

[][]Switch ON the main power switch.
[][]Switch ON the blower by pressing green button of the machine.
[][]Then switch ON the motor by pressing green button of the machine.
[][]Input the material through the hopper of the machine manually.
[][]Sieve the material and collect sieved material through the cover discharge opening.
[][]After operation first switch OFF the motor then switch OFF the blower by pressing red button.
[][]Record the machine operation parameters in the ‘Equipment Log Book’.

Machine Dismantling

[][]Open the front cover of the machine.
[][]Remove the sieve ring of the machine.
[][]Remove the filter bag of the machine.
[][]Remove the tray of the machine.

Machine Cleaning

[][]Remove dusts from the machine body and other necessary parts with a vacuum cleaner.
[][]Clean all the machine parts with dry lint free cloth.
[][]Use potable water to clean the machine body, product contact parts, tray, container, sieve & filter bag.
[][]Use hot water to clean all the product contact parts such as sieve ring.
[][]Finally rinse the machine body, product contact parts, trays and other machine parts with purified water.
[][]Remove the water with lint free cloth.
[][]After final cleaning affix the ‘CLEANED’ label.
[][]Record the cleaning parameters in the ‘Equipment Log Book’.

Annexure:

Annexure I Equipment Use Log Book

Material Pulverization Machine Set Up, Operation & Cleaning Read More »

Bottle Drying Machine Set Up, Operation & Cleaning

Bottle Drying Machine, Purpose :

Bottle Drying Machine, The purpose of this SOP is to describe the setting, operation and cleaning procedure of the Glass Bottle Drying Machine (Model: Standard) in order to comply with cGMP standard.

Bottle Drying Machine, Scope :

The scope of the procedure is applicable to the Glass Bottle Drying Machine (Model: Standard) at the Production area of XX Pharmaceuticals Limited.

Definitions / Abbreviation:

N/A.

Responsibilities:

[][]The Roles and Responsibilities are as follows:

Operator

[][]Sep Up, Operation and cleaning of the Glass Bottle Drying Machine (Model: Standard)
[][]Maintaining Equipment Log Book

Executive, Production

[][]To monitor and check the laid down procedure.

Manager, Production

[][]To implement this correctly

Manager, Quality Assurance

[][]To approve the Document

Procedure
Precautions :

[][]Make sure that the main power switch is OFF position before and after operation.
[][]Use face mask, rubber gloves and protective clothing during handling of materials.
[][]Check the cleanliness of individual tray and machines inner part during assembling of machine.
[][]Booth side doors are in lock position during operation.
[][]Check the air outlet damper position before and after completion of operation.

Machine Assembling

[][]Keep the necessary change parts near the material dryer machine before assembling.
[][]Assemble the dryer by opening the front side door of the dryer.
[][]Load tray with glass bottle and place into the tray holding rack.
[][]Then set the rack carrying trolley.
[][]Then place the tray holding rack into the machine.
[][]After that closed the door accurately with the help of door locking handle.
[][]Then closed the air outlet damper and tight the screw accurately.

Machine Operation

[][]Switch ON the main power switch.
[][]Open the plastic cover and set the desire temperature of the machine.
[][]Then open the plastic cover and set the desire time of the machine.
[][]At first switch ON the blower of the machine.
[][]Then switch ON the heater of the machine.
[][]After completed the drying time open the air outlet damper for bottle cooling and check the bottle.
[][]After operation switch OFF the heater and then blower. Unload the tray holding rack from the machine.
[][]Finally switch OFF the main power of the machine.
[][]Record the machine operation parameters in the ‘Equipment Log Book’.

Machine Dismantling

Open the both side door of the machine.
Unload the tray holding rack from the machine with the help of carrying trolley.
Remove the tray from the rack.

Machine Cleaning

Clean all the machine parts with dry lint free cloth.
Use potable water to clean the machine body, product contact parts, tray and other machine parts.
Use hot water to clean all the trays.
Finally rinse the machine body, product contact parts, trays and other machine parts with purified water.
Remove the water with lint free cloth.
After final cleaning affix the ‘CLEANED’ label.
Record the cleaning parameters in the ‘Equipment Log Book’.

Annexure:

Annexure I Equipment Use Log Book

Bottle Drying Machine Set Up, Operation & Cleaning Read More »

Bottle Washing Machine Set Up, Operation And Cleaning

Bottle Washing Machine, Purpose :

Bottle Washing Machine, The purpose of this SOP is to describe the setting, operation and cleaning procedure of Glass Bottle Washing Machine (Model: IRW-16) in order to comply with cGMP standard.

Bottle Washing Machine, Scope :

The scope of the procedure is applicable to the Glass Bottle Washing Machine (Model: IRW-16) at the Production area of XX Pharmaceuticals Limited.

Definitions / Abbreviation:

N/A.

Responsibilities:

[][]The Roles and Responsibilities are as follows:

Operator

[][]Set up, operation and cleaning of the Washing Machine (Model: IRW-16)
[][]Maintaining Equipment Log Book

Executive, Production

[][]To monitor and check the laid down procedure.

Manager, Production

[][]To implement this correctly

Manager, Quality Assurance

[][]To approve the Document

Procedure

Precautions :

[][]Make sure that the main power switch is OFF position before and after operation.
[][]Use face mask, rubber gloves and protective clothing during handling of materials.
[][]Check the cleanliness of individual water reserve tank and machines inner part during assembling of machine.
[][]Do not touch the hot water tank during operation.
[][]Check the individual bottle washing nozzle working properly.

Machine Assembling

[][]Keep the necessary change parts near the bottle washing machine before assembling.
[][]Assemble the washing machine by bottle holder.
[][]Load the pump 1 with tap water and pump 2 with hot water.
[][]Load the bottle holder with glass bottle.
[][]Set the nozzle’s spray rate of tap water and purified water depending on the glass bottle size.

Machine Operation

[][]Switch ON the main power switch.
[][]Switch ON the heater switch of the machine and wait 20 minutes for hot water (60ºC).
[][]Then press the START button of the main motor.
[][]After press the START button of the pump 1.
[][]Then press the START button of the pump 2.
[][]Open the valve of compressed air line.
[][]After completing the glass bottle washing procedure close the valve of tap water, purified water & compressed air line.
[][]After operation switch OFF the heater, pump 2, pump 1 and then main motor.
[][]Finally switch OFF the main power of the machine.
[][]Record the machine operation parameters in the ‘Equipment Log Book’.

Machine Dismantling

[][]Open the cover of the machine.
[][]Remove the bottle holder of the machine.
[][]Drainage the water of pump 1 & pump 2.

Machine Cleaning

[][]Remove dusts from the machine body and other necessary parts with a vacuum cleaner.
[][]Use potable water to clean the machine body, product contact parts and other machine parts.
[][]Use hot water to clean all the parts.
[][]Finally rinse the machine body, product contact parts and other machine parts with purified water.
[][]Remove the water with lint free cloth.
[][]After final cleaning affix the ‘CLEANED’  label.
[][]Record the cleaning parameters in the ‘Equipment Log Book’.

Annexure:

Annexure I Equipment Use Log Book

Bottle Washing Machine Set Up, Operation And Cleaning Read More »

Blister Packaging Machine Set Up, Operation & Cleaning

Blister Packaging Machine, Purpose :

Blister Packaging Machine, The purpose of this SOP is to describe the setting, operation and cleaning procedure of the Blister Packaging Machine (Model: HM-V3) in order to comply with cGMP standard.

Blister Packaging Machine, Scope :

The scope of the procedure is applicable to the Blister Packaging Machine (Model: HM-V3) at the Production area of XX Pharmaceuticals Limited.

Definitions / Abbreviation:

N/A.

Responsibilities:

[][]The Roles and Responsibilities are as follows:

Operator

[][]Set Up, Operation and cleaning of the Blister Packaging Machine (Model: HM-V3)
[][]Maintaining Equipment Log Book

Executive, Production

[][]To monitor and check the laid down procedure.

Manager, Production

[][]To implement this correctly.

Manager, Quality Assurance

[][]To approve the Document.

Annexure:

N/A.

Procedure

Precautions :

Safety

[][]Never run the machine with its door open.
[][]Use face mask, rubber gloves and protective clothing during handling of materials.
[][]Keep the switches “OFF” during break-time and at the end of the job.
[][]Care must be taken to ensure that the drive units and accessory parts cannot be switched on inadvertently after servicing or maintenance work.

Special Instruction

[][]Be sure that the power switches are “OFF” position.
[][]Beware of the high temperature of “Sealing top mold” during cleaning and if possible, allow it to cool down completely.
[][]Should not use methanol or other organic solvent like ethanol, carbon tetrachloride, thinner, benzene etc. to clean plastic doors and other parts of the machine.
[][]Water should not be used to clean metal parts of the machine.
[][]Care should be taken to ensure that no water enters inside the motor.
[][]Corrosive materials should not be used to clean the machine.
[][]Heavy parts should not dismantle alone, always taken help from others.
[][]Machine chiller purified water level should be check fifteen days interval and purified water should be change every three months interval.
[][]Carefulness should be taken about heavy parts handling.

Machine Assembling

[][]Switch on the main power supply of the machine.
[][]Check the draw in of the base film and the lid foil.
[][]Check Compressed air valve open and air pressure above 6 bars.
[][]Turn control panel key “ON”.
[][]Push reset button and press main button.
[][]Press setup button to show password for entering product list.
[][]Select Specific product from product list and press main button.
[][]Adjust draw off length by pressing inching switch according to advance length.
[][]Check the emergency push buttons, safety switches of the safety guards/glass doors.
[][]Press Main button and enter into information and positioning the machine according to following parameter-
[][]Forming station
[][]Sealing station
[][]Embossing
[][]Cooling station
[][]Perforation / Slitting station.

[][]Set following change parts by push inching switch-
Forming
Perforation / Slitting
Cutter
[][]Set following change parts carefully-
Pre-heating
Guide rail
Sealing upper-lower plate.
Embossing
Cooling Plate
Pulling Station
Feeding Tray

[][]Push reset button and checks the machine accurately by inch the inching switch press.
[][]Set bottom foil & lid foil and cutting shall be adjusted by inching switch on manual mode with press-
Heater.
Chiller.
Draw off.
Sealing lift.
[][]Press “Start” button and run machine to check the pocket forming and batch code embossing.
[][]Insert tablets or capsules on the pocket of PVDC/PVC/ALU film on the guide rail and perform a leak test operation of those strips to ensure proper sealing.
[][]Press manual mode and “OFF” all button only the following button shall “ON”
Heater.
Chiller and
Sealing lift.
[][]Convert manual mode to auto mode for running the machine.
[][]After completed the all parts setting, check that every parts are setting properly & proper place.
[][]Ensure that every screw nuts are tight properly.
[][]Set batch code with the respective digit.
[][]Emboss batch code and show Quality Assurance Officer for approval.

Machine Operation

[][]Ensure that area and equipment are clean and suitable to start the operation.
[][]Before starting the blister machine use surgical gloves, nose mask etc.
[][]Set different change parts like forming plate, sealing plate, code embossing, guid rail, cooling plate etc. in proper position.
[][]Set the top Foil (Alu foil) & Bottom Foil (PVC, PVDC & Alu foil) correctly.
[][]Open the compressed air valve & ensure that the air pressure is above 6 bars. Check & ensure that the compressed air is free from moisture.

[][]Temperature for PVDC preheating 110-140ºc and sealing 150-180ºc and for slitting are 60-80ºc & embossing Alu 70-80 ºc, temperature for Alu sealing 160-180 ºc and embossing 70-90 ºc maintained .
[][]Tablets and Capsules are placed manually to the PVDC forming or Alu forming pocked. Different packs are produced for different products by forming, feeding, sealing, punching and discharging.
[][]Machine should be observed very carefully during blistering operation.
[][]Press the stop button in machine after completes the blister operation.
[][]Record the machine operation start time and end time & other parameters in the ‘Equipment Log Book’ .

Dismantling of Change Parts

[][]Change parts should be removed sequentially from the machine with the help of others.
[][]Feeding Tray should be removed by loosing screw nuts.
[][]Guide Rail should be removed by loosing nuts.
[][]Forming Set (Upper & Lower Plate) should be removed by loosing screw nuts.
[][]Cutter should be removed by loosing nuts.
[][]Sealing Upper Plate should be removed by loosing clamp lock.
[][]Sealing Lower Plate should be removed by loosing screw nuts.
[][]Cooling Plate should be removed by loosing screw nuts.
[][]Perforation/ Slitting should be removed by loosing screw nuts.
[][]Heating Plate (In-case of Alu-PVC) should be removed by loosing nuts.
[][]Embossing Plate should be removed by loosing screw nuts and clamp lock.
[][]Change parts should be kept on clean pallets with “TO BE CLEANED” label.

Machine Cleaning

[][]All documents, previous product container and any materials should be removed from the room.
[][]The dust should be cleaned around the machine with the help of vacuum cleaner.
[][]The surface of the machine should be cleaned with lint free cloths with Purified Water or defined cleaning solution starting from top to downwards sequentially at first ceiling, wall, machine and floor.
[][]Safety covers (Door) should be cleaned by the use of wetted smooth lint free cloth with purified water.
[][]Glass and plastic materials should be cleaned by lint free smooth cloth with purified water.
[][]The machine should be moped with a lint free cloth using purified water.
[][]Finally, the machine should be moped with dried lint free cloth.
[][]Record should be taken in equipment machine log book.
[][]Machine accessories should be transferred to the wash room.
[][]“CLEANED” label should be attached to the machine.
[][]Change parts should be dismantled and kept on a clean trolley or pallets with status label and kept the trolley on the washing room for the cleaning at the end of product run.
[][]After cleaning completion the change parts should be stored in tool store with “CLEANED” label.

Annexure:

Annexure I Equipment Use Log Book

Blister Packaging Machine Set Up, Operation & Cleaning Read More »

ROPP Cap Sealing Machine Set Up, Operation & Cleaning

ROPP Cap Sealing Machine, Purpose :

ROPP Cap Sealing Machine, The purpose of this SOP is to describe the Operation and cleaning procedure of ROPP Cap Sealing Machine (Model: PPM-35) in order to comply with cGMP standard.

ROPP Cap Sealing Machine, Scope :

The scope of the procedure is applicable to the ROPP Cap Sealing Machine (Model: PPM-35) at the Production area of XX Pharmaceuticals Limited.

Definitions / Abbreviation:

N/A.

Responsibilities:

[][]The Roles and Responsibilities are as follows:

Operator

[][]Setting, operation and cleaning of the Cap Sealing Machine (Model: PPM-35)
[][]Maintaining Equipment Log Book.

Executive, Production

[][]To monitor and check the laid down procedure.

Manager, Production

[][]To implement this correctly

Manager, Quality Assurance

[][]To approve the Document

Procedure:

Precaution:

[][]Ensure that area & equipment are clean and suitable to start the operation.
[][]Use protective suit, surgical gloves, head gear, cotton mask, and safety goggles during sealing operation.
[][]In case of emergency, press the emergency switch to stop the machine.

Machine Assembling

[][]Set the base of the machine by specific nut and attach the bottle adjuster.
[][]Set the sealing wheel according to the neck diameter of the bottle.
[][]Fix the bottle size by moving the base.

Machine Operation

[][]Load the bottle on the SS table.
[][]Fix the plastic stopper and aluminum cap on the empty bottle.
[][]Turn on the main switch of the machine.
[][]Take a bottle on the base.
[][]Seal it by the moving sealing wheel.
[][]Check the leakage by leak test apparatus.
[][]If sealing is accurate then another eight empty bottle have to seal.
[][]Take them again for leak test.
[][]Continue the sealing operation if sealing is accurate.
[][]Turn off the all switch gradually after complete the sealing operation.
[][]Record the machine start & end time and other parameters in the ‘Equipment Log Book’

Machine Dismantling

[][]Turn the main switch off.
[][]Dismantle the parts like moving sealing wheel, bottle adjuster unit and transfer them to the wash bay.

Machine cleaning

[][]Remove dusts from the machine with a vacuum cleaner. Collect dust from machine body.
[][]Clean all the machine parts with dry lint free cloth.
[][]Use potable water to clean the machine body and holding screw.
[][]Use hot water to clean all the product contact parts & finally rinse with purified water.
[][]Clean and swab all the parts with lint free cloth to remove water.
[][]After final cleaning affix the ‘CLEANED’ label.
[][]Record the cleaning parameters on the ‘Equipment Log Book’.

ROPP Cap Sealing Machine Set Up, Operation & Cleaning Read More »