Material Requisition Procedure to Ware-House

Material Requisition Procedure, Purpose: Material Requisition Procedure, To lay down the procedure for raising Requisition of Material to the Ware-House. Material Requisition Procedure, Scope: This SOP is applicable for the Production Area  of the XX Pharmaceuticals Limited. Definitions / Abbreviation: [][]N/A Responsibilities: [][]The Roles and Responsibilities are as follows: Operator [][]To follow the laid down […]


Material Requisition Procedure, Purpose:

Material Requisition Procedure, To lay down the procedure for raising Requisition of Material to the Ware-House.

Material Requisition Procedure, Scope:

This SOP is applicable for the Production Area  of the XX Pharmaceuticals Limited.

Definitions / Abbreviation:

[][]N/A

Responsibilities:

[][]The Roles and Responsibilities are as follows:

Operator

[][]To follow the laid down procedure

Executive, Production

[][]To monitor and check the laid down procedure

Manager, Production

[][]To Implement this correctly

Manager, Quality Assurance

[][]To approve the Document

Procedure:

[][]Material Requisition shall be raised in following cases.
[][]On line rejection: If approved raw material or packing material issued for the batch is rejected on line due to quality defects like black particles in raw material, hard lumps, smudged printing or no  printing on printed materials like foil, carton, insert, label and shipper and color variation beyond acceptable shade.
[][]Material consumed more than standard: In case dispensed raw material is compensated due to spillage, spray pipe leakage during coating, excess coating material and packaging materials required for recovery addition, excess foil consumption during blister pack machine setting, excess carton consumption during manual cartooning, printing problem of carton, catch cover, insert and shipper carton.
[][]Production Executive shall raise ‘Material Requisition’ (Annexure-I) by writing all details with reason in the ‘Remarks’ column and shall sign in ‘Requisitioned by’ row.
[][]Material Requisition (MR) shall have duplicate copy. First copy shall be mentioned as ‘Ware-House Copy’ at right top corner of Material Requisition form. Second copy shall be mentioned as ‘Batch Record Copy’ at right top corner of Material Requisition form.
[][]Head of Quality Assurance (QA) or his/her designate shall justify the reason for MR and will approve accordingly.
[][]Approved Material Requisition shall be sent to dispensing for Issuance.
[][]After Issuance of materials ‘Batch Record’ copy shall be attached with Batch Manufacturing Record (BMR) & Batch Packaging Record (BPR) and ‘Ware-House Copy’ shall be sent to Ware-House for stock adjustment purpose.

Annexure:

Annexure I –Material Requisition.